CONTRACT AWARD DISCLOSUREREPORT
Name of Project: National Water DevelopmentProject II (Malawi)
Project ID: P096336
Contractdescription:
Feasibility studies, preliminary and detailed design of raw water sourcefor Chitipa and
expansion works for Chitipa, Chilumba, Rumphiand NkhataBay Water Supply Schemes
Scope of contract:
The works willinvolve design and construction supervision of rehabilitation, upgrading and
construction of intake works, treatment plants,transmission mains, storage tanks, distribution
pipelines, auxiliary buildings, and extension ofdistribution system to newly developed areas.
The Consultants are also expected to carry outfinancial and economic analysis of the project,
review and update Business Plans prepared by the NorthernRegion Water Board, undertake
consultations so that stakeholders provide input tothe project and carry out environmental/social
impact screening.
| Disclosure Report for Contract Awarded by QCBS |
| Name & address of consultant/firm | Technical score | Financial score | Final evaluated price (US$) | Final Ranking |
| IGIP in association with Bua Consulting Engineers Dolivostraße 11 64293 Darmstadt Germany | 79.5% | 100% | 493,300.28 | 1 |
| SNC Lavalin 2275 Upper Middle Road East Oakville, Ontario CANADA, L6H 0C3 | 67.8% | N/A* | N/A* | N/A* |
WinningConsultant: IGIP in association with Bua Consulting Engineers
Contract Price: US$ 525,782.77 (US$ 235,857.24 lump-sum contractand
US$ 289,925.53 time-based) inclusiveof taxes
Duration: 30 months (6 months design, 3 monthstendering, and 9 months construction
supervision and 12 monthsdefect liability period)
Contract signature date: 24thApril 2008
*The firm did not qualify to have itsfinancial proposal opened and evaluated